Mataf Extension

Mataf Extension

Optimizing Comfort at Makkah Haram During Mataf Expansion

The Mataf area in Makkah Haram is a critical space for pilgrims performing Tawaf around the Holy Kaaba. With the increasing number of visitors during Hajj and Umrah seasons, ensuring optimal cooling and reliable power supply is essential for maintaining comfort and safety. Saudi ProTech was entrusted with the supply and installation of a temporary HVAC system and electrical infrastructure for the Mataf Extension project, under the leadership of Bin Laden Group and Johnson Control as the main contractor.

Completed in 2014, this project focused on enhancing cooling efficiency and stable power distribution to accommodate the large influx of pilgrims during the Mataf expansion.


Project Overview

Project Details

  • Project Name: Mataf Extension
  • Location: Makkah Haram, Saudi Arabia
  • Year: 2014
  • Owner: Bin Laden
  • Main Contractor: Johnson Control
  • Project Status: Handed Over
  • Scope of Work:
    • Temporary HVAC System Supply & Installation
    • Electrical System Supply & Installation
    • Testing & Commissioning

Project Objectives

Saudi ProTech was responsible for:

  • Providing a temporary HVAC system to ensure optimal cooling for pilgrims.
  • Installing a reliable electrical system to support the HVAC and lighting requirements.
  • Executing the project with minimal disruption to the ongoing religious activities.
  • Ensuring safety and comfort for pilgrims during the Mataf expansion.

Project Challenges

  • Maintaining consistent cooling in a crowded and open space environment.
  • Executing electrical installations without disrupting the existing infrastructure.
  • Ensuring system efficiency under heavy usage during peak seasons.
  • Complying with safety and operational regulations in a sacred site.

Scope of Work: HVAC & Electrical Implementation

1. Temporary HVAC System: Cooling for the Mataf Area

Due to the high temperatures and large number of pilgrims, effective cooling was a critical requirement for the Mataf Extension. Saudi ProTech designed and installed a temporary HVAC system tailored to the unique needs of the site.

A. HVAC System Design & Installation

  • Conducted heat load analysis to determine optimal cooling capacity.
  • Designed a modular temporary cooling system that could be easily installed and dismantled as needed.
  • Installed large capacity temporary chillers and air handling units (AHUs) to distribute cool air across the Mataf area.

B. Air Distribution & Ventilation

  • Set up temporary ducting networks for efficient air distribution.
  • Installed fans and air diffusers to ensure even cooling coverage in crowded areas.

Key Benefits:
Enhanced Pilgrim Comfort: Maintains a cool and comfortable environment despite high temperatures.
Scalable Solution: Modular design allowed for easy adjustments based on crowd density.
Energy Efficiency: Optimized cooling performance reduced energy consumption.


2. Electrical System: Reliable Power Supply for Temporary HVAC

A stable electrical system was necessary to power the temporary HVAC units and ensure uninterrupted operation.

A. Electrical Power Supply & Installation

  • Installed temporary power distribution panels to manage the electrical load of the HVAC system.
  • Designed dedicated circuits for HVAC, lighting, and other temporary needs.
  • Implemented backup power solutions to prevent downtime during peak usage.

B. Load Management & Safety Measures

  • Conducted load balancing to ensure stable power distribution across the system.
  • Installed voltage regulators to prevent power surges and ensure system safety.

Key Benefits:
Reliable Power Supply: Prevents interruptions in cooling services during peak pilgrim times.
Safe Operation: Meets the safety standards required for high-density public spaces.
Efficient Power Usage: Smart load management reduces energy waste.


Testing, Commissioning & Handover

After installation, Saudi ProTech conducted a comprehensive testing and commissioning process to ensure the temporary systems operated at peak efficiency.

A. HVAC System Testing

  • Verified cooling performance across the Mataf area.
  • Ensured even air distribution in high-density zones.

B. Electrical System Validation

  • Conducted load testing to confirm stable power supply.
  • Checked voltage stability and surge protection for safe operation.

Successfully handed over a fully operational temporary HVAC and electrical system to support the Mataf Extension during the Hajj season.


Key Benefits of the Mataf Extension Project

1. Enhanced Comfort for Pilgrims

  • Consistent cooling provided relief from high temperatures during Tawaf.
  • Optimized air distribution ensured a comfortable environment for all visitors.

2. Reliable Power Infrastructure

  • Stable electrical supply prevented disruptions in cooling services.
  • Smart load management ensured efficient energy usage.

3. Seamless Integration & Minimal Disruption

  • Quick installation and removal of temporary systems ensured minimal impact on religious activities.
  • Compliance with safety standards guaranteed safe operations in a sacred space.

Conclusion: A Benchmark in Temporary MEP Solutions for Sacred Sites

The Mataf Extension HVAC & Electrical Project at Makkah Haram demonstrates Saudi ProTech’s capability to deliver customized, energy-efficient, and reliable temporary solutions for large-scale public events and sacred sites. Our expertise in MEP installations ensured that pilgrims experienced a comfortable and safe environment during their spiritual journey.

Looking for Expert Temporary MEP Solutions?

Saudi ProTech specializes in tailored HVAC, electrical, and MEP solutions for large-scale events, sacred sites, and high-occupancy public spaces.

📞 Contact us today to discuss your project needs and discover how we can enhance your facility with cutting-edge MEP technology.